Villa project
STAGES OF PERFORMANCE WORKS:
August 2017.
Preparing for the excavation
August 2017.
Fencing of the site area with a grid
07 августа 2017 г. Начало раскопок
November 16, 2017
Excavation of the pit
20 November 2017
Installation of a septic tank
December 11, 2017.
Formwork for the foundation
December 15, 2017.
Wooden formwork for the foundation.
Foundation construction
December 22, 2017
Arrangement of formwork and installation of reinforcement for the subsequent pouring of concrete
December 26, 2017
Construction of the pool. Pipe installation
December 28, 2017
Filling of concrete for the foundation of the house and pool
January 3, 2018.
Concrete screed road fill
March 6, 2018.
Completion of foundation work
March 9, 2018.
Foundation Pouring
March 28, 2018
Installation of reinforced concrete and the bay of concrete on the terrace of category C 20/25
April 20, 2018
Bricklaying
May 16, 2018
Installation of electrical equipment
May 17, 2018
Plumbing installation
June 06, 2018
Installation of heated floor
July 02, 2018
Fill screed
July 10, 2018
Construction of retaining walls
July 23, 2017
Reinforcement for pouring concrete around the house for laying stone.
July 26, 2018
Bay of concrete category c16 / 20 around the house (sidewalks).
Filling of the base under a bath.
July 29, 2018
Laying stone and grouting.
August 7, 2018
Laying floor tiles.
15.August.2018
Filling the road to the site, concrete category c20 / 25
Facing the pool bowl tiled
September 03, 18
September 5, 2018
Plumbing installation (installation of bath and toilet)
September 15, 2018
Installation of solar panels for water heating, swimming pool, heat pump and air conditioners in the house.
28 September 2018




Installation of interior doors
30 September 2018




Interior filling
Installation of kitchen furniture and kitchen electrical equipment