Project Description:
- The total are of plot of land is 10 000 sq.m.
- The total area of the each house is 130 sq.m.
- Floors: 1
- Pools:2 х 30 cub.m.
- Construction term: 15 months.
- Beginning of design March 2017.
- Start of construction: November 2017.
Design concept:
STAGES OF PERFORMANCE WORKS:
November 2017. Site preparation for excavation
November 29, 2017. Archaeological site verification
December 1, 2017. Planning the site before construction
December 6, 2017. Installation of septic tanks (volume 9 cubic meters each)
December 18, 2017. Construction of retaining walls
January 10, 2018. Fill of draft concrete of category C 12/15
to prepare the formwork
January 18, 2018. Construction of retaining walls.
Continuation of work
January 23, 2018. Construction of pools (formwork)
February 03, 2018. Installation of reinforcement for pool formwork
February 10, 2018. Pouring of concrete category C 20/25 C 500 (swimming pools)
February 13, 2018.
Unloading lumber
for the construction of a wooden frame house
February 14, 2018. Outdoor waterproofing pools
May 14, 2018. Start of formwork
May 23, 2018. Pouring of concrete category C 20/25 (house foundation)
June 3, 2018. Continuation of foundation works
June 5, 2018. Pipe installation
July 16, 2018. Building walls of a frame house
July 20, 2018. Continuation of work
August 31, 2018. Plumbing installation
September 12, 2018
Laying with fireplace wool for thermal insulation and sound insulation, using Tyvek insulation film to protect against water and moisture.
September 13, 2018
Installation of intercontact plasterboard partitions in two layers of the brand Knauf, to enhance the strength and sound insulation.
Masoning tile brand Imola ceramica. Grouting joints.
October 04, 2018
October 13, 2018
Installation (installation) of aluminum windows and Alumil doors
“08” November 2018
Ground planning over the land area.
Preparation for pouring concrete.
Interior filling
Pouring industrial concrete