Construction of a villa with a pool in the village of Kastri, Heraklion region

Villa project

 

STAGES OF PERFORMANCE WORKS:

August 2017.

Preparing for the excavation

 

August 2017.

Fencing of the site area with a grid

07 августа 2017 г. Начало раскопок

         

November 16, 2017

Excavation of the pit

 

20 November 2017

Installation of a septic tank

    

December 11, 2017.

Formwork for the foundation

December 15, 2017.

Wooden formwork for the foundation.

Foundation construction

December 22, 2017

Arrangement of formwork and installation of reinforcement for the subsequent pouring of concrete

December 26, 2017

Construction of the pool. Pipe installation

December 28, 2017

Filling of concrete for the foundation of the house and pool

January 3, 2018.

Concrete screed road fill

March 6, 2018.

Completion of foundation work

March 9, 2018.

Foundation Pouring

March 28, 2018

Installation of reinforced concrete and the bay of concrete on the terrace of category C 20/25

April 20, 2018

Bricklaying

May 16, 2018

Installation of electrical equipment

May 17, 2018

Plumbing installation

 

June 06, 2018

Installation of heated floor

 

July 02, 2018

Fill screed

July 10, 2018

Construction of retaining walls

 

July 23, 2017

Reinforcement for pouring concrete around the house for laying stone.


July 26, 2018

Bay of concrete category c16 / 20 around the house (sidewalks).

Filling of the base under a bath.

July 29, 2018

Laying stone and grouting.

 

August 7, 2018

Laying floor tiles.

15.August.2018

Filling the road to the site, concrete category c20 / 25 

 

Facing the pool bowl tiled

September 03, 18

 

September 5, 2018

Plumbing installation (installation of bath and toilet)

September 15, 2018

Installation of solar panels for water heating, swimming pool, heat pump and air conditioners in the house.

 

House painting

28 September 2018

 


Installation of interior doors
30 September 2018